Our Diagrams
Figure 1 (Week 1)
Gannt Chart 1
Key tasks:
Method Selection and Planning (High Priority)
Start: 2024-02-19, End: 2024-03-15
Includes Research, Planning, Gantt Chart Creation, Documentation
Dependencies: None
Website Creation (Medium Priority)
Start: 2024-02-24, End: 2024-03-01
Includes Domain creation on Github, Website Design
Dependencies: None
Risk Management (Medium Priority)
Start: 2024-02-25, End: 2024-03-15
Includes Introduction, Writing Risks, Documentation
Dependencies: None

Figure 2 (Week 2)
Gannt chart 2
Key tasks:
Requirement Collection (High Priority)
Start: 2024-03-06, End: 2024-03-19
Includes Customer Interviews, Writing User/System Requirements, Documentation
Dependencies: None
Implementation (Highest Priority)
Start: 2024-02-28, End: 2024-04-11
Includes Menu Creation, Map/Navigation Design, Character Design/Movement, Collision Detection, Interior Design, Map Transitions, Integration
Dependencies: Requirement Collection

Figure 3 (Week 3)
Gannt Chart 3
Key tasks:
Architecture (High Priority)
Start: 2024-03-10, End: 2024-03-21
Includes System Design, Database Design
Dependencies: None
Links Creation (Low Priority)
Start: 2024-03-16, End: 2024-03-16
Dependencies: Implementation, Website Creation, Architecture, Risk management, Method selection and planning

Figure 4
Architecture
Post Client Interview Class Diagram